Quiz #8

How to protect your house from flooding course quiz:

1) What is retrofitting?

          a) Rebuilding your house.
b) Making changes to an existing building to protect it from flooding or other hazards such as high winds and earthquakes.

c) Changing the appearance of your house to fit the neighborhood.

2)
Storm surge is:

  a) High winds associated with hurricanes
b) The rise in the level of the ocean that results from the decrease in atmospheric pressure associated with hurricanes and other storms.

c) High winds associated with tornadoes.

3)
Which one of the items below is an important flood characteristic?

  a) Depth/elevation
b) Flow
c) Velocity
d) Frequency
e) Rate of rise and rate of fall
f) Duration
g) Debris load
h) All of the above

4)
In Fig 2.6 the 100-year flood elevation for the house shown is 391.6 feet. According to survey the elevation of the lowest floor of the house is 389.3 feet. The flood depth above the lowest floor is therefore equal to:

  a) 2.3 feet during the 100-year flood.
b) 7.8 feet any time it rains and flood the area
c ) 10.1 feet during the 100-year flood

5)
In fig 2-7; during a flood hydrostatic pressure acts on walls and the bouncy force pushes against slab from underneath. In homes with a basement, saturated soils add to the pressure on basement walls and concrete slab.

  a) True
b) False

6)
According to table 3-2 the cost of elevating a frame house 2 feet off the ground on Slab-on-grade foundation is approximately:

  a) $47.00 ft.2
b) $17.00 ft.2
c) $35.00 ft.2

7)
Wet flood proofing a house is modifying

  a) A house against the rain
b) The uninhibited section of the house such as crawlspace or unfinished basement so that the flood waters will enter but not cause significant damage to either the house or its contents.

8)
Fig 3.7 and 3.8 show two examples of wet floodproof house. The purpose of allowing water enter into portions of the house is to ensure that the interior and exterior hydrostatic pressure on the walls will be equal.

  a) True
b) False
 
9) According to table 3.4, the cost of wet flood proofing a masonry house up to 8 ft above the ground/basement floor with a basement foundation is:

  a) $1.70 ft.2
b) $3.50 ft.2
c ) $10.00 ft.2

10) Figure 3-11 shows:

  a) The picture of a house protected by a levee built around a house, which has hold back, the floodwaters.

b) An aerial view of a boat house

11
)  Figures 5-4a through 5-4d show the procedure for elevating a house with crawlspace foundation
  a) True
b) False

12
) Figures 5-6a through 5-6d show the procedure for elevating a house with a slab-on-grade foundation

  a) True
b) False

13) Dry floodproffing is completely sealing the exterior of a building to prevent the entry of floodwaters. Successful dry flood proofing involves which one of the following:

  a) Sealing the exterior walls of the house
b) Covering openings bellow the flood level
c ) Protecting interior of the house from seepage
d ) Protecting service equipment outside the house
e ) All of the above

14)  Figure 7-7 and 7-8 show how an asphalt sealant is used in dry flood proofing a masonry wall.

  a) True
b) False

15)  Figure 7-9 shows how a temporary layer of polyethylene film is used to wrap around the house, to stop the flood water entering the house.

  a) True
b) False

------------------------------------------------Ethics Section --------------------------------------------


16)  In case #11; It was alleged that Mr. Doe, a Texas PE engineer, altered boundary information on Survey plats for a subdivision that had been prepared by a license surveyor, affixed a copy of the surveyor’s seal to the plats and submitted the plats to county officials for approval without knowledge of the surveyor. The Board reportedly suspended his license for one year and fined him $1000.00

  a) True
b) False

17)  In case # 15; It was alleged that Jim, the company’s president, designed seven swimming pools and affixed a copy of a Texas Professional engineer’s seal and signature that he had obtained from another source to the plan sheets which were submitted to a city for permitting. Board records did not show that Jim was licensed as a professional engineer in Texas nor that his company had Texas professional engineer as a regular full-time employee. The Board accepted an Agreed Board Order signed by Jim to cease and desist from any and all representations that his company can offer and/or perform engineering services and from the actual performance of engineering services until such time as the company hires a Texas licensed professional engineer as a regular full time employee, and to immediately discontinue the use of the Texas professional engineer’s seal and signature on any and all documents. Jim also agreed to hire a Texas professional engineer to perform after the fact engineering inspections and issue certification reports for the five swimming pools that were permitted and constructed. The company was also ordered to pay a $5000.00 administrative penalty.

  a) True
b) False

18)  In case #17; John was a registered engineer in:

  a) Texas
b) Michigan
b) New Mexico

19)  In case #21; It was alleged that Billy signed his name and affixed his Texas Architectural seal to structural, mechanical, electrical and plumbing design plans for renovation of a commercial building. Based upon the size of the building, the structural, mechanical, electrical and plumbing designs were required by law to have been performed by a licensed professional engineer; therefore Billy’s preparation of these design plans constituted the unlawful practice of engineering. The Board accepted a consent order signed by Billy and his attorney agreeing that Billy will not practice engineering outside the exemption listed in the Engineering practice Act and will refrain from making any and all representations that he can offer and/or perform engineering services until such time as he hires a Texas licensed professional engineer as a regular full time employee or until such time as he becomes a Texas licensed professional engineer. Billy also agreed to pay a $1000.00 administrative penalty.

  a) True
b) False

20)  In case #6; It was alleged that Jim provided professional engineering design services in connection with residential foundation design and exterior wall systems during a period when his Texas engineer license was expired. The Board accepted a Consent Order signed by Jim for a two-year probated suspension of his Texas engineer license contingent upon his payment of a $2000.00 administrative penalty.

  a) True
b) False

21)  In case #7; It was alleged that Dr. Smith conducted an engineering inspection for his client in December 1998; but did not provide his client with his inspection report until February 2000. This Indicated that he was not acting as a faithful agent for his client and his actions were not in keeping with generally accepted engineering standards and procedures. The Board accepted a Consent Order signed by Dr. Smith for a formal reprimand.

  a) True
b) False

22)  In case # 24; John-David-Bill, Inc. It was alleged that site grading and drainage plans for two projects were submitted to the city of Brownsville, one set bearing John’s signature and architect seal and the other bearing David’s signature and architectural seal. The size and scope of the respective projects required that Texas licensed professional engineers prepare the grading and the drainage design plans. Board records did not show any of the three were licensed as professional engineers in Texas nor that their company had any regular full time employees who were licensed as professional engineers in Texas. Therefore it appears these individuals unlawfully performed engineering services and their respective plans were an unlawful representation of their company’s ability to offer and /or perform engineering services.
The Board accepted a Consent order signed by the president of the company to cease and desist from practice of engineering and from any and all representations that the company can offer of performing engineering services until the such time as the firm hires a full time employee who is licensed as a professional engineer in Texas. The company also agreed to pay a $2000.00 administrative penalty.

  a) True
b) False

If you would like a hard copy of your quiz answer sheet, please print this web page before clicking on the "Grade Me" button above.

You need to get at least 70% of the questions correct to pass.

 